The ANEEL Research & Development Program allocates specific resources to electricity companies (EEE), specifically transmission companies, 0.4% of their net operating revenues, with the aim of promoting a culture of innovation, stimulating research and development in the Brazilian electricity sector, creating new equipment and improving the provision of services that contribute to the security of electricity supply, tariff affordability and the reduction of the sector's environmental impact. Argo works in partnership with several research institutions, supporting national technological development, aligned with the company's strategy and the guidelines of the Research and Development Program regulated and supervised by ANEEL.

We currently have 5 projects running in the lines of research: Electricity Services Quality and Reliability, Electricity Systems Operation, New Technologies for Electricity Systems Maintenance and Inspection, and Electricity Systems Planning. Click here (Portuguese Only) to learn about the projects in progress.

For further information contact us: pdi@argoenergia.com.br.

  Project Own or Cooperate* Start date Date expected for completion Status**
Download Insulators Own May/2020 Apr/2025 Under execution
Download SIASE-T ABRATE Cooperative May/2022 Mar/2025 Under execution
Download VIVO Own Aug/2022 Aug/2025 Under execution
Download Corrosiveness Own Sep/2022 Mar/2026 Under execution
Download Market Capacity ABRATE Cooperative Sep/2022 Sep/2024 Concluded
Download SE's teleassistance (robot) Own Sep/2023 Sep/2026 Under execution
Download Insulating Oil Analysis Own Nov/2023 Nov/2026 Under execution
Download Reliability Own Sep/2018 Aug/2020 Concluded

* Own project: Cooperative project between Argo Group companies;
ABRATE Cooperative Project: Strategic sector project in which we participate as a cooperating company and management of the Abrate Institute;
** Projetos em execução na data base do relatório, março/2024